Haberkorn Rd construction

Friday, August 5, 2022


TYPEConstruction
STARTTuesday, July 12, 2022 7:00 AM
ROADHaberkorn Rd
LENGTH4.71 mi
DESCRIPTIONProject - Road closed / For length of Work Zone

On Haberkorn Rd from Balltown Rd to South Mound Rd
On South Mound Rd from Haberkorn Rd to Sherrill Rd

8/5/22 UPDATE: The culverts are completed and the road is open between Balltown Rd &Riegler Rd. Paving operations for the entire road section, with flaggers and pilot cars, is estimated to start on Wednesday, August 11th. The estimated duration of the paving project is 2-3 weeks depending on weather. Shouldering and pavement markings to follow.